Project highlight
132kV Feeder 9L3 Oran Park
Detailed Information
Largest concrete poles installed on the Endeavour Energy network. Part of the line traversed a flood plain with water as little as 500mm below the surface.
Gremalco assisted Endeavour Energy in the design of specialised foundations for these areas and installed foundations that were up to 2m diameter and 5.9 deep.
Testimonials